To be continued ...

Text Size: AaAaAaAaAa

PRINCETON — A final decision on whether to extend the conditional use permits for the proposed Walnut Ridge wind farm will not be made until at least March 17.

More than 100 people filled the large courtroom in the Bureau County Courthouse Monday night for the resumed Zoning Board of Appeals meeting. The meeting had begun Feb. 17, but was recessed after 30 minutes because the developer of the project did not have legal counsel.

Project manager Bill French was back for the 7 p.m. meeting with his legal counsel, Jim Griffin, at Monday’s meeting as were attorneys Tom Boswell and Rick Porter. Boswell and Porter were representing a coalition of Friesland Farms, Larry Gerdes and other objectors to the Walnut Ridge project.

The Walnut Ridge conditional use permits and associated variations were granted to the Midwest Wind Energy developers in August 2008, November 2008 and December 2008 for 150 turbines, two staging areas, two substations and 99 transmission line support structures. The permits and variations expire after three years, so Walnut Ridge came before the board to request an extension of the permits until Dec. 31, 2014.

Bureau County State’s Attorney Pat Herrmann said the board would first consider whether Walnut Ridge had a “vested interest” in the project. According to Bureau County rules, if a conditional use permit has not been acted upon or exercised within three years, and if “there is little or no vesting of interest,” the permit becomes null and void.

Griffin said Walnut Ridge was continuing with the development of the project, but wanted confirmation the permits would remain valid.

“We want absolutely no uncertainty as to our zoning rights,” he said.

Griffin said Walnut Ridge has spent $3.2 million on the project since receiving the permits, and is moving forward to full development.

Griffin then called French to testify. French said that, to date, the company has executed leases with landowners, erected four more meteorological towers, conducted soil borings and environmental studies, analyzed the electric grid connection, negotiated underground pipeline and highway crossing agreements, and was soon to purchase the substation sites.

French said part of the reason the project isn’t further along is that the country is still coming out of a huge economic downturn. French said that downturn caused lending institutions to change their requirements before lending.

Previous Page|1|||

Comments


National Video