Wastewater issues on SV’s table
SPRING VALLEY — Spring Valley’s water treatment plant has been working well with the anti-scalent treatment, and the new reverse osmosis membranes are ready to be installed.
“Most of the week will be taken up with replacement,” city engineer Jack Kusek said at this week’s council meeting.
Kusek expects the membranes to be replaced later this month, which should take four to five days. The treatment plant must be operational during the switch, so it will be a slow and planned process.
The city is also working on various concrete projects at the wastewater treatment plant. City employees are repairing the stoop and steps that have deteriorated after decades of use. They are also replacing a concrete slab to the grit chamber.
In other water treatment business at the meeting, the council announced it is finally operating its wastewater treatment plant with a MPDS permit after months of wrangling. The city lost its permit after not filing the proper paperwork in time and has been operating without one.
The city engineer has been working to have the permit reinstated, but the new permit came with several new special conditions, including monitoring levels of ammonia. Kusek said the Illinois Environmental Protection Agency used to just give waivers, but it’s making cities work for them now.
“They’re just not issuing the permit,” Kusek said at Monday’s meeting.
Kusek said the city will not meet ammonia standards, which states wastewater runoff must have less than 3.3 milligrams per liter of ammonia in March through May and September through October, 3 milligrams per liter from June through August and 3.8 milligrams per liter from November through February.
In the past this was never tested because the IEPA assumed the river would be enough to dilute the ammonia, but the agency is now requiring cities to prove it. Kusek didn’t believe the city would have any problems making its case.
High levels of ammonia in the water can lead to rapid plant growth and possible toxicity to fish, Kusek said.
Kusek said he has almost completed a draft proposal for cleaning up the city’s wastewater sludge using enzymes. He hopes to have the contract awarded in March and begin using the enzymes in April. The city has about 72,000 cubic yards of sludge in the treatment plant lagoon, and it’s causing the city to be out of compliance with suspended solid levels.
Also, a building that protects the sewer outlet to the river needs extensive repair after being hit by a barge. Kusek said it’s partially submerged, and the city needs to work with the Army Corps of Engineers to get a permit to work on it. City employees will not be able to do the work; Kusek said the city will get a contractor.
Comment on this story at www.bcrnews.com.
In other business:
• The city’s backup well No. 10 needs repairs, and the council approved a proposal by Albrecht Well Drilling. Since it is considered an emergency, they did not have to go out to bid for the project, which is expected to cost $40,000.
• The city council approved reissuing bonds for the city hall, fire truck and sewer repair at a lesser interest rate. The move will save the city about $65,000 in interest by dropping the interest rates from 4.72 to 2.45. The move does not decrease or increase the term on the bonds.
• The city is taking bids in early March for a plan to replace the water main near St. Bede. Kusek said there have been several leaks over the years, and that section needs to be replaced.
• The council approved paying $13,121 to Argubright Construction for sewage treatment plant improvements.
• There will be a finance committee meeting at 6:30 p.m. Feb. 21 to discuss the 2012 levy followed by a legislative committee meeting to discuss personnel.
• Police chief Kevin Sangston said he is looking for two people to serve on the CrimeStoppers Board.
Comments
Total Comments 0 View/Add Comments |
There have been no comments made about this story. |










