Illinois Department of Transportation representative Steve Andrews (from left) responds to questions from Spring Valley Mayor Cliff Banks, Alderman Dan McFadden and city engineer Jack Kusek at Tuesday's public meeting, held at the Spring Valley City Hall. City officials, businessowners and residents attended the meeting to learn of IDOT's plans for replacing the Route 89 bridge over the Illinois River. (BCR photo/Barb Kromphardt)
Buy Bureau County Republican Photos »

Fultz said after Phase I is finished, Phase II usually takes an additional 18 to 24 months before construction could begin.

“For a major river bridge, it may require additional reviews by the Corps of Engineers and the Coast Guard,” Fultz said.

Construction itself is projected to last at least two construction seasons.

Comment on this story at www.bcrnews.com.